Timelines

  • Any mail received shall be replied within 24-48 hrs depending on the data needed
  • Concept design – Will be closed in 10 working days which involves DBR, budget cost, MEP space
  • Detailed design – Will be closed in 15 working days which involves finalisation of DBR, layout plan of typical floor for all MEP services. Will work closely with architects and other consultants to get data and incorporate in MEP design.
  • Tender – Will be closed in 15 working days post getting approval on DD stage deliverables
  • Queries from vendors, Prebid query reply, closure of vendor technical evaluation process shall be given in 1 or 2 working days
  • GFC drawings shall be parallelly done post Tender. Will work closely with architects and other consultants to get data and incorporate in MEP design. GFC drawings will be shared as MEP coordinated drawing. Normally will take 30 working days
  • Above timelines shall vary based on approvals received from other team and depending on project requirement